Optimization of the time of the start of projects realization at the limited resources

Authors

A. I. Kosolap
Дніпропетровський національний університет
D. H. Kushnarenko
Дніпропетровський національний університет

Keywords

project models ranging optimization purpose function clipping multiextremal problems quadratic relaxation software

Abstract

We consider complex dynamic problem of performing the set of commercial projects in case of limited resources. This problem is transformed into multiextreme one, effective algorithms are suggested for its solution. Applied software is developed for solution of this problem.
271 146

How to Cite

[1]
“Optimization of the time of the start of projects realization at the limited resources”, Вісник ВПІ, no. 3, pp. 62–65, Nov. 2010, Accessed: Oct. 03, 2026. Available: https://visnyk.vntu.edu.ua/index.php/visnyk/article/view/751

Author Biographies

A. I. Kosolap, Дніпропетровський національний університет

доцент кафедри комп’ютерних технологій

D. H. Kushnarenko, Дніпропетровський національний університет
студентка кафедри комп’ютерних технологій

Most read articles by the same author(s)